“When will the court be ready?” depends far less on how fast the installation crew works than on where the project waits. What usually stretches the schedule is not production but slab preparation, changes of mind and permits. Below is the route from order to first serve, with the factor that governs each step.

What are the stages of a padel court installation?

StageWhat happensWhat governs the duration
1. SurveyArea, ground condition, court count, layoutHow quickly information and photos arrive
2. Quotation and contractScope fixed, model and options chosenDecision time, the most common delay
3. SlabNew platform poured or existing slab preparedWeather and concrete curing
4. ProductionSteel structure, glass and components manufacturedModel, court count, production schedule
5. ShippingLoading and delivery to siteDistance; customs for export
6. InstallationStructure, glass, turf and lightingCourt count, site access, weather
7. HandoverChecks, maintenance briefing, warranty documents

What really stretches the schedule?

Three things: the slab, the decision and the weather. Pouring the platform and letting it reach strength is the least compressible item; it is planned, not shortened. Second come decisions on the client side: a change of model, an extra court or a change of location sends the project back to the start. Third is weather, which stops both concrete work and installation. Plan those three properly and the rest runs predictably.

How much faster is it with an existing slab?

Considerably. If a sound platform within tolerance already exists, the longest item drops out and the project moves straight to production and installation. This is why tennis court and pitch conversions complete noticeably faster than new builds. Suitability is judged on the age of the concrete, the state of the surface and the difference in levels.

Does the facility have to close during installation?

No; in an operating facility the work is normally phased. The work area is separated, noisy operations are scheduled outside peak hours and an access route is agreed for materials. In hotels and clubs the healthiest approach is to install outside the season or during a low-occupancy period. Access constraints (narrow gates, lifts, positions needing a crane) affect duration directly, so they are noted at survey stage.

What is handed over at completion?

  • Check list: dimensions, net height, glass and fixing inspection
  • Written warranty: ten years on the steel structure, five on the turf, two on other components
  • Maintenance schedule and a short briefing for your site team
  • Copies of production and product certificates on request

Tell us your area and ground condition and we will map out the schedule with you.

HAVE A PROJECT IN MIND?

We can build this project for you too.

QUOTE FORM

Tell us your project, your price ready in 24h.

We prepare exact pricing based on location, ground condition and number of courts.

Your details are used only to prepare your quote and are never shared.

CALL NOW