Most problems on a padel court originate not in the glass, the steel or the turf but in the concrete. A platform outside level tolerance builds stress into the glass fixings; poor drainage shortens the life of the surface. This article explains why the slab is decisive and what a proper specification must contain.

How flat does the slab have to be?

The critical requirement is that the surface sits in a single plane across the whole court. Local dips and humps are felt through the turf and disturb the bounce; differences in level make the structure’s feet work under unequal loads. So “flat concrete” is not a specification: the measurement method, the acceptable deviation and how levels are taken must all be written down. The platform is also larger than the court itself; clearance is left for installation and anchorage.

Where does the water go?

On an outdoor court, drainage decides the life of the surface more than the turf specification does. There are two approaches: a graded platform that directs surface water to drainage channels, or a drained base that removes water from below. Any fall is kept limited and in one direction so it does not affect play. Water pooling at the court edge attacks the concrete and anchorages through freeze-thaw cycles, so discharge points are fixed at design stage.

Ground conditionWhat can be doneWatch for
New concrete platformPoured to specificationCuring time enters the schedule
Existing sound concreteUsually reusableAge, cracking and level checks are essential
AsphaltAssessed case by caseLoad capacity and surface deterioration
Pitch / clay courtNew platform requiredRemoving the existing base is a separate item
Soil / fillExcavation, fill, concreteSettlement risk; compaction is critical

Why is anchorage a separate subject?

The structure is fixed to the slab with anchors, and wind load is transferred through those points. If the strength or thickness of the concrete is inadequate for the anchor, the problem appears at the connection rather than in the court. If a roof is planned, loads increase further, so the roof support positions and anchorage capacity must be designed together with the platform. If you may add a roof later, say so at project stage; it saves substantial cost.

What should the specification contain?

  • Net platform dimensions and the position of the court on it
  • Surface flatness tolerance and measurement method
  • Level plan, direction of fall and water discharge points
  • Concrete class, thickness and reinforcement
  • Anchorage zones and the strength required
  • Electrical provisions: conduit and box positions for lighting poles

Request the slab specification for your project; we send it with the pre-installation check list.

HAVE A PROJECT IN MIND?

We can build this project for you too.

QUOTE FORM

Tell us your project, your price ready in 24h.

We prepare exact pricing based on location, ground condition and number of courts.

Your details are used only to prepare your quote and are never shared.

CALL NOW